Solarpark Wyandot Solar

Capacity:
12 MW
Country:
USA
State:
Ohio
Commissioning:
2010
Modules:
159200

juwi developed, designed and built the Wyandot Solar Energy Facility, a 12.0 MWp solar PV facility located in Upper Sandusky, Ohio. In June 2009 juwi’s subsidiary executed a 20-year PPA with AEP Ohio. Construction commenced in the fourth quarter of 2009, and the project achieved commercial operation in May 2010.

  • juwi’s construction group, together with a leading Ohio-based subcontractor, commenced construction in October 2009
  • Includes 159,200 ground-mounted, thin-film solar panels on 77-acre plot of land
  • Commercial operation occurred on May 26, 2010
  • In September 2009, juwi transferred its ownership rights in the project to PSEG Solar Source
  • Energy and REC off-taker is AEP Ohio
  • juwi is currently operating, maintaining and monitoring the project on behalf of PSEG Solar Source

Back to list

More topics

Solar

Newest article

juwi Hellas inaugurates three PV plants 8,6MWp

juwi Hellas has successfully constructed, commissioned and put into commercial operation three PV... more

Strategic Realignment in juwi Australia

Cameron Garnsworthy appointed Managing Director of juwi Renewable Energy Pty Ltd. more

AREAM acquires Perl Wind Park from project developer juwi

Perl consists of six Enercon wind turbines with an installed capacity of 18 MW / The first three... more


Subscribe as RSS feeds