Solar

Solarpark Wyandot Solar

Capacity:
12 MW
Country:
220
State:
Ohio
Commissioning:
2010
Modules:
159200

juwi developed, designed and built the Wyandot Solar Energy Facility, a 12.0 MWp solar PV facility located in Upper Sandusky, Ohio. In June 2009 juwi’s subsidiary executed a 20-year PPA with AEP Ohio. Construction commenced in the fourth quarter of 2009, and the project achieved commercial operation in May 2010.

  • juwi’s construction group, together with a leading Ohio-based subcontractor, commenced construction in October 2009
  • Includes 159,200 ground-mounted, thin-film solar panels on 77-acre plot of land
  • Commercial operation occurred on May 26, 2010
  • In September 2009, juwi transferred its ownership rights in the project to PSEG Solar Source
  • Energy and REC off-taker is AEP Ohio
  • juwi is currently operating, maintaining and monitoring the project on behalf of PSEG Solar Source

Back to list

More topics

Newest article

juwi to construct wind and solar farm in regional Western Australia

The hybrid project consists of a renewable energy hub which will include a 4 megawatt solar farm… more

Strategic reorientation of juwi is beginning to bear fruit: Now leading international project developer for solar power plants

The focused growth strategy of the company is paying off/ juwi is occupying top positions on current… more

juwi O&M services to provide MoreSun® AR Shield in cooperation with Pellucere Technologies

more